Question: All planned orders in a given week are converted into production orders. a. true b. false 35. While completing an MRP record, you find that,
All planned orders in a given week are converted into production orders. a. true b. false
35. While completing an MRP record, you find that, in Week 5, the gross requirement is 70, and projected available balance for Week 4 is 14. Lot size is 70, lead time is 2 weeks. Which of the following will you enter in the planned order release row?
a. 56 in week 3
b. 56 in week 5
c. 56 in week 5, 70 in week 3
d. 70 in week 5
e. 70 in week 3