Question: All the following statements describe a schedule management plan except: It details the scheduling methodology that will be used on the project. It identifies schedule
All the following statements describe a schedule management plan except:
It details the scheduling methodology that will be used on the project.
It identifies schedule change control procedures.
It must be issued as a formal and detailed document.
It establishes a plan for managing schedule variances.