Question: All work must be submitted in Excel format Q1 (30pts). Given the following information, draw the projects network diagram in both AOA and AON format:
All work must be submitted in Excel format
Q1 (30pts). Given the following information, draw the projects network diagram in both AOA and AON format:
| Activity | Immediate Predecessor |
|---|---|
| 1 | -- |
| 2 | -- |
| 3 | 1, 4 |
| 4 | 2 |
| 5 | 2 |
| 6 | 3, 5 |
Q2. (40pts) Given the following AOA diagram below, convert it to AON diagram and find:
(a) The critical path (b) How long it will take to complete the project (c) The ES, LS, EF, and LF for each activity (d) The slack for each activity
Q3. (30pts) Consider the scenario of you finding a new job in a new company. You are treating this as a project. For this project, you are the project manager, and some of the tasks include the following: deciding the job requirements that fit your profile, updating your CV, interview preparations, setting up your CV on the job portal, and signing up for job alerts. Other tasks may include reviewing your CV with career center personnel, and signing up with career center for job opportunities. There are various stages/tasks while finding a new job ranging from deciding on a company based on culture, location, salary, and benefits to getting ready with interview preparations and making arrangements for the interview travel.
Consider this project from the project managers viewpoint and prepare a Work Breakdown Structure (WBS) for the project. Enter the tasks and divide each task into subtasks (with more details). Include dependencies between tasks. Indicate hours of work, status, start date, and planned, estimated, and actual completion dates using MS Excel spreadsheet. Also make sure you indicate at least 5 subtasks for these tasks. Some of the tasks are included below.
1. Registering with the career center
2. Reviewing your CV with the career center
3. Decide on the new job requirements & company profile
4. Updating your CV & identifying and resolving the gaps
5. Setting up your updated CV on job portal sites & sign-up for the job alerts
6. Preparing for interview (interview techniques, skills, knowledge, future plans)
7. Making travel arrangements & getting ready with your work portfolio
8. Conducting the interview
9. Following up after the interview
10. Negotiating the offers you receive
11. Deciding on the best offer
In all, the number of tasks and subtasks is expected to be 25. You need to indicate at least 6 dependencies among the tasks. Develop a project work breakdown structure (WBS) for the project scenario in Excel spreadsheet in appropriate format.