Question 1:
Given the following information, draw the AON diagram:
\table[[Activity,Immediate Predecessor],[1,-],[2,-],[3,1,4],[4,2],[5,2],[6,3,5]]
Question 2:
4. Given the diagram below, find:
(a) The critical path.
(b) How long it will take to complete the project.
Question 3:
7. Given the following activities and precedences, draw an AOA or AON diagram:
Activity Immediate Predecessor
\table[[A,-],[B,-],[C,A],[D,A, B],[E,A, B],[F,C],[G,D, F],[H,E, G]]
Question 4:
9. Given the estimated activity times below and the network in Problem 8 above,
\table[[Activity,a,m,b
 Question 1: Given the following information, draw the AON diagram: \table[[Activity,Immediate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!