Question: Allocate overhead costs using activity rates for different cost pools. Activity Cost Activity Driver Driver Quantity Setup activities $80,000 Number of setups 800 setups Machine
Allocate overhead costs using activity rates for different cost pools.
Activity | Cost | Activity Driver | Driver Quantity |
Setup activities | $80,000 | Number of setups | 800 setups |
Machine processing | $300,000 | Machine hours | 15,000 hours |
Quality control | $50,000 | Number of inspections | 2,000 inspections |