Question: An 11-activity PERT network with activity mean and variance as shown below in Figure 1. Assume all activities are stochastically independent and Z 0.95 =

An 11-activity PERT network with activity mean and variance as shown below in Figure 1. Assume all activities are stochastically independent and Z 0.95 = 1.645.

An 11-activity PERT network with activity mean

Which are the shortest, and longest PERT paths? What are their lengths?

B 19,25) ESH (5,) 7,25) E (5) (7,25) > (19,90 (10,1 (3,) 13,1) I JK (10,7) (3) (14,9) (4,25) D D (8,64) (7,36) (7,36) Figure 1 Figure 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!