Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =48, LF C = 57; activity times are
A = 4, B = 6, C = 8 a. 37 b. Insufficient information c. 40 d. 38 e. 42