Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,EF C=42,LFB=51,LFC=55; activity times are A=4,B=6,C=8 a. 43 b. Insufficient information C. 45 d. 41 e. 40