Question: An activity has a duration estimate that is best case = 30 days, most likely =44 days, and worst case= 62 days. What is the

An activity has a duration estimate that is best case = 30 days, most likely =44 days, and worst case= 62 days. What is the expected activity time?

A) 34.67 days

B) 44.67 days

C) 5.33 days

D) 59.33 days