Question: An activity has a duration estimate that is best case = 30 days, most likely =44 days, and worst case= 62 days. What is the
An activity has a duration estimate that is best case = 30 days, most likely =44 days, and worst case= 62 days. What is the expected activity time?
A) 34.67 days
B) 44.67 days
C) 5.33 days
D) 59.33 days