Question: An activity has a duration estimate that is best case = 5 days, most likely = 12 days, and worst case=15 days. What is
An activity has a duration estimate that is best case = 5 days, most likely = 12 days, and worst case=15 days. What is the Triangular three-point estimate for this activity in days?
Step by Step Solution
There are 3 Steps involved in it
The Triangular threepoint estimate for the activity can be calculated by using the formula Triang... View full answer