Question: An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic

An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is 10, then the expected time for the activity is
A. about 10 days
B. about 14 days
C. about 19 days
D. about 23 days
E. about 24 days
F. about 28 days