Question: An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic
An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time. If the activity variance is then the expected time for the activity is
A about days
B about days
C about days
D about days
E about days
F about days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
