Question: Q2. (5 pts.) An activity has a pessimistic time that is four times as long as its most likely time and seven times as long

Q2. (5 pts.) An activity has a pessimistic time
Q2. (5 pts.) An activity has a pessimistic time that is four times as long as its most likely time and seven times as long as its optimistic time. If the activity variance is 16, what is the expected time? (show your work.) A) 5 B) 6 C) 7 D) 8 E) 9 F) None of the above