Question: An activity has eight weeks allotted to it, but we should be able to do it in five weeks. Waiting 3 1/2 weeks before getting
An activity has eight weeks allotted to it, but we should be able to do it in five weeks. Waiting 3 1/2 weeks before getting started on it is an example of the:
A. Project buffer approach B. Feeder buffer approach C. Professor approach D. Academic approach E. Student syndrome