Question: An activity on a PERT network has these time estimates: optimistic = 1.8, most likely = 3.3, and pessimistic = 10. What is its expected

An activity on a PERT network has these time estimates: optimistic =An activity on a PERT network has these time estimates: optimistic = 1.8, most likely = 3.3, and pessimistic = 10. What is its expected activity time and variance? (Do not round intermediate calculations. Round final answer to two decimal places.)

An activity on a PERT network has these time estimates: optimistic =1.8, most likely =3.3, and pessimistic =10. What is its expected activity time and variance? (Do not round intermediate calculations. Round final answer to two decimal places.) A. 4.17;1.87 B. 0.33;4.10 C. 2.36;1.37 D. 7.55;4.20 E. 2.73;2.05

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!