Question: An activity on a PERT network has these time estimates: optimistic = 1.8, most likely = 3.3, and pessimistic = 10. What is its expected
An activity on a PERT network has these time estimates: optimistic = 1.8, most likely = 3.3, and pessimistic = 10. What is its expected activity time and variance? (Do not round intermediate calculations. Round final answer to two decimal places.)
An activity on a PERT network has these time estimates: optimistic =1.8, most likely =3.3, and pessimistic =10. What is its expected activity time and variance? (Do not round intermediate calculations. Round final answer to two decimal places.) A. 4.17;1.87 B. 0.33;4.10 C. 2.36;1.37 D. 7.55;4.20 E. 2.73;2.05
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts