Question: Question 3 6 ( 2 points ) An activity on a PERT network has these time estimates: optimistic = 2 , most likely = 3
Question points
An activity on a PERT network has these time estimates: optimistic most likely and pessimistic Its expected time and variance if it is a critical activity are
Question options:
;
;
;
;
;
Question points
A PERT project has activities, of which are on the critical path. The estimated time for the critical path is days. The sum of all activity variances is while the sum of variances along the critical path is The probability that the project can be completed between days and is
Question options:
Question points
An activity on a PERT network has these time estimates: optimistic most likely and pessimistic Its expected time is
Question options:
Question points
If an activity whose normal duration is days can be shortened to days for an added cost of $ the crash cost per period is
Question options:
$
$
$
$
$
Question points
A project being analyzed by PERT has activities, of which are on the critical path. If the estimated time along the critical path is days with a project variance of the probability that the project will take days or less to complete is
Question options:
near zero.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
