Question: Question 3 6 ( 2 points ) An activity on a PERT network has these time estimates: optimistic = 2 , most likely = 3

Question 36(2 points)
An activity on a PERT network has these time estimates: optimistic =2, most likely =3, and pessimistic =8. Its expected time and variance (if it is a critical activity) are
Question 36 options:
43.3; 1.
4.33; 6.
4.33; 1.
3.67; 6.
3.67; 1.
Question 37(2 points)
A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is
Question 37 options:
0.0227.
0.1058.
0.9773.
0.4773.
-2.00.
Question 38(2 points)
An activity on a PERT network has these time estimates: optimistic =2, most likely =5, and pessimistic =10. Its expected time is
Question 38 options:
5.00.
0.533.
5.33.
5.67.
17.00.
Question 39(2 points)
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500, the crash cost per period is
Question 39 options:
$1,500.
$500.
$13,000.
$750.
$15,000.
Question 40(2 points)
A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the critical path is 176 days with a project variance of 144, the probability that the project will take 194 days or less to complete is
Question 40 options:
2.00.
0.0668.
near zero.
0.9332.
0.0126.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!