Question: An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is the variance

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is the variance of activity completion time? Group of answer choices 0.44 0.83 1.67 2.50 3.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!