Question: An activity on a PERT network has these time estimates: optimistic = 2 , most likely = unknown, and pessimistic = unknown. If variance =

An activity on a PERT network has these time estimates: optimistic =2, most likely = unknown, and pessimistic =unknown. If variance =4 and expected time =10, what are the most likely and pessimistic estimates?