Question: An activity on a PERT network has these time estimates: optimistic = 2 , most likely = unknown, and pessimistic = unknown. If variance =
An activity on a PERT network has these time estimates: optimistic most likely unknown, and pessimistic unknown. If variance and expected time what are the most likely and pessimistic estimates?