Question: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 10. What is its expected
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 10. What is its expected activity time and variance?
A. 4; 10.67
B. 5; 10.67
C. 5; 1.78
D. 4; 1.78
E. None of the Above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
