Question: An activity on a PERT network has these time estimates: optimistic (best) =4 days, most likely =6 days, and pessimistic (worse) =12 days. What are

An activity on a PERT network has these time
An activity on a PERT network has these time estimates: optimistic (best) =4 days, most likely =6 days, and pessimistic (worse) =12 days. What are the approximate expected time and variance of this activity? Expected time =7.33 and variance =1.78 Expected time 6.67 and variance =1.78 Expected time =6.67 and variance =0.22 Expected time =7.33 and variance =8