Question: An activity on a probablistic time network diagram has these time estimates: optimistic = 2 , most likely = 3 , and pessimistic = 1

An activity on a probablistic time network diagram has these time estimates: optimistic =2, most likely =3, and pessimistic =10. What is its expected activity time and variance?
Expected time: 4
Variance: 1.78
Expected time: 5
Variance: 1.33
Expected time: 4
Variance: 10.67
Expected time: 5
Variance: 1.78
Expected time: 5
Variance: 10.67