Question: Consider the following project activities: Calculate the expected time (t e ) for each activity. Draw an Activity on Node (AON) diagram to reflect the
Consider the following project activities:

- Calculate the expected time (te) for each activity.
- Draw an Activity on Node (AON) diagram to reflect the flow of these activities.
- Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity.
- Calculate the slack for each activity.
- Identify all activities on the Critical Path.
- Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score).
Please do not handwrite. Please use word doc or excel.
Activity A 8 D E F G H Duration (weeks) Predecessor Optimistic Most Likely Pessimistic 1 2 A 2 7 A 1 3 5 B 3 6 9 C 2 3 7 A 5 7 EF 4 8 D 1 3 GH 2 6 MIN ANStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock