Question: An advertising project manager has developed a program for a new advertising campaign. Calculate the expected activity times. Calculate the activity slacks. What is the

An advertising project manager has developed a program for a new advertising campaign.

Calculate the expected activity times.

Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network.

Identify the critical path. What are the alternative paths, and how much slack time is associated with each non-critical path?

Identify the burst activities and the merge activities.

Given the activity variances, what is the likelihood of the project finishing on week 24?

Suppose you wanted to have 99% confidence in the project finishing on time. How many additional weeks would your project team need to negotiate for in order to gain this 99% likelihood?

Online classes are difficult to learn. I would hand written answers and explanation for each question.

An advertising project manager has developed a

Time Estimates (week) Activity Optimistic Most Pessimistic Likely Immediate Predecessor(s) 1 4 7 B 2 6 10 3 3 9 B D 6 13 14 E 4 6 14 AC F 6 6 8 16 B B G N 5 8 D. EF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!