Question: An analyst has timed a metal - cutting task for 5 0 cycles. The average time per cycle was 1 1 . 3 minutes, and

An analyst has timed a metal-cutting task for 50 cycles. The average time per cycle was 11.3 minutes, and the standard dev 1.35 minutes for a worker with a performance rating of 135 percent. Assume an allowance of 11 percent of task time. Calcul standard time for this task. (Do not round intermediate calculations. Round the final answer to 2 decimal places.)Standard time