Question: An analyst while preparing the cumulative operating cash flow diagram for a project , came across the following information Construction phase is 3 years Operations

An analyst while preparing the cumulative operating cash flow diagram for a project , came across the following information Construction phase is 3 years Operations phase is 20 years Payback period is 15 years Calculate the length of the tail of the project The analyst feels the tail is too short . Do you agree ? why