Question: An app developer company has a project with the following activities list. ( Times in days ) table [ [ Activity , Preceding,Time ]

An app developer company has a project with the following activities list. (Times in days)
\table[[Activity,Preceding,Time],[A,--,8],[B,--,3],[C,A,7],[D,A, B,3],[E,C,4],[F,D,6]]
a. Draw the network diagram.
b. Calculate the ES, EF, LS, LF, and Slack for each activity.
c. What is project completion time?
 An app developer company has a project with the following activities