Question: An app developer company has a project with the following activities list. (Times in days) Activity Preceding Time A -- 8 B -- 3 C

  1. An app developer company has a project with the following activities list. (Times in days)

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A, B

3

E

C

4

F

D

6

a. Draw the network diagram.

b. Calculate the ES, EF, LS, LF, and Slack for each activity.

c. What is project completion time?