Question: An approved Project Charter does NOT: Authorize the Project Team to expend organizational resources on project activities. Serve as a Request for Quote ( RFQ

An approved Project Charter does NOT:
Authorize the Project Team to expend organizational resources on project activities.
Serve as a Request for Quote (RFQ) for external vendors to bid on project activities and deliverables.
Clarify the key goals and objectives of the project.
Authorize the existence of the project.