Question: An assembly consists the following elements as given in table below. The daily customer demand is 300 units and the line works for 8 hours

An assembly consists the following elements as given in table below. The daily customer demand is 300 units and the line works for 8 hours per day. Task - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Immediate - - 1 3 3 3 3 4 5 6 2,7 8 9 12,13 10,11 14,15 predecessor Task 20 77 73 150 88 15 20 66 25 55 71 47 32 24 50 38 time (sec) C. b. List the sequential relationship among tasks and draw the precedence diagram. (15) Calculate the cycle time and minimum number of work station. (10) d. Assign the task to the workstations using LCR method. (30) e. Calculate the line efficiency (15) f. Is it possible to reduce the cycle time to achieve the daily demand? Analyze it. (30)