Question: An assembly line has 24 work elements that total 360 minutes and the desired cycle time has been computed to be 115 minutes/unit. The work

An assembly line has 24 work elements that total

An assembly line has 24 work elements that total 360 minutes and the desired cycle time has been computed to be 115 minutes/unit. The work elements are loaded into workstations and the minimum number of workstations are used. The average workstation time is 90 minutes and the longest workstation time is 96 minutes, what is the efficiency of this assembly line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!