Question: An assembly line has 24 work elements that total 360 minutes and the desired cycle time has been computed to be 115 minutes/unit. The work

An assembly line has 24 work elements that total 360 minutes and the desired cycle time has been computed to be 115 minutes/unit. The work elements are loaded into workstations and the minimum number of workstations are used. The average workstation time is 90 minutes and the longest workstation time is 102 minutes, what is the efficiency of this assembly line? Note: Answer to in decimal format (3 decimal places) like 0.678 NOT 67.8%.