Question: An assembly line has three operations in sequence. The work-centers take 4, 3, and 2 minutes per job. (So job 1 enters the first work-center,

An assembly line has three operations in sequence. The work-centers take 4, 3, and 2 minutes per job. (So job 1 enters the first work-center, where it takes 4 minutes; then it is moved to the second work center where it takes 3 minutes while job 2 enters the first work-center, etc.)

In the above line, if the second work-center operation time is reduced by ten percent, what is the throughput of this line (as number of jobs completed per hour in the long run)?