Question: An assembly line that operates for 840 mins with a number of tasks has to be configured. The total of all task times is 83
An assembly line that operates for 840 mins with a number of tasks has to be configured. The total of all task times is 83 mins and the longest task time is 10 mins and the shortest is 4 mins.
What is the largest cycle time that will ensure a daily output of 52 units?
Then what is the minimum number of stations needed to make sure there is a output of 52?