Question: An assembly line which operates for 840 minutes with a number of tasks is to be configured. The sum of all the task times is

An assembly line which operates for 840 minutes

An assembly line which operates for 840 minutes with a number of tasks is to be configured. The sum of all the task times is 72 minutes. The longest task time is 8 minutes and the shortest task time is 2 minutes. What is the smallest possible cycle time for this assembly line? Answer: Continuing: What is the maximum possible daily output for this assembly line? Report as a whole number by rounding