Question: An assembly line with 15 tasks is to be balanced. The longest task is 3 minutes, and the total time for all tasks is 15

An assembly line with 15 tasks is to be balanced. The longest task is 3 minutes, and the total time for all tasks is 15 minutes. The line will operate for 449 minutes per day. a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Answer is complete but not entirely correct. b. What range of output is theoretically possible for the line? (Round your answers to whole numbers.) Answer is complete but not entirely correct. c. What is the minimum number of workstations needed if the maximum output rate is to be sought? (Round your answer up to a whole number.) Answer is complete but not entirely correct. d. What cycle time will provide an output rate of 128 units per day? (Round your answer to 1 decimal place.) Answer is complete but not entirely correct
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts