Question: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 17

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 17 minutes. The line will operate for 500 minutes per day. a. What is the minimum number of workstations needed if the output rate is to be 172 units per day? (Round the final answer to the next whole number.) Number of workstation b. What cycle time will provide an output rate of 128 units per day? (Round the final answer to 2 decimal places.) Cycle time minutes per unit c. What output will result if the cycle time is (i) 11 minutes? (ii) 16 minutes? (Round the final answers to the next whole number.)

Output of 11 Min CT units per day
Output of 16 Min CT units per day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!