Question: An assembly line with 60 activities is balanced using 13 workstations and a finished product can be produced every 6.0 minutes. The total amount of

 An assembly line with 60 activities is balanced using 13 workstations

An assembly line with 60 activities is balanced using 13 workstations and a finished product can be produced every 6.0 minutes. The total amount of time to complete all 60 activities is 40 minutes. The line will operate for 480 minutes per day. Round your answers for the following questions to one decimal place. a. What is the production rate in units per day? units/day b. What is the assembly line efficiency? %