Question: An assembly process is receiving the incorrect pieces for assembly. To ensure that only the correct pieces are sent, the parts tub is redesigned so

An assembly process is receiving the incorrect

An assembly process is receiving the incorrect pieces for assembly. To ensure that only the correct pieces are sent, the parts tub is redesigned so that only the correct pieces (at their correct number) can fit into the tub. This is an application of: a. Error proofing/Poke yoke. b. Standard work. c. Visual factory. d. 5S

Step by Step Solution