Question: An assembly task was broken down into four elements, and timed using the continuous timing method. The resulting data and performance ratings are provided below.

An assembly task was broken down into four elements, and timed using the continuous timing method. The resulting data and performance ratings are provided below. Calculate the total standard time for this task.
Element 1234
Watch Time 1.852.965.427.10
Observed Time
Rating 95105120115
Normal Time Total ST
Standard Time

Step by Step Solution