Question: An educational publisher is developing a new biology program with separate components for the students and for the teachers. The project manager creates Schedule A
An educational publisher is developing a new biology program with separate components for the students and for the teachers. The project manager creates Schedule A for the development of the student components. She then sets the starting date of Schedule B for the teacher components at the halfway point of Schedule A Which type of workplace theory is the project manager most likely using?
Process
Personality
Method
Development