Question: An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical

An electrical contractor pays his subcontractors a
fixed fee plus mileage for work performed. On a given
day the contractor is faced with three electrical jobs
associated with various projects. Given below are the
distances between the subcontractors and the projects.
Projects
Subcontractor A B C
Westside 503616
Federated 283018
Goliath 353220
Universal 252514
How should the contractors be assigned so that total
mileage is minimized?
Provide a network representation for the assignment
problem (with supplies/demand and costs or distances
shown)
Formulate it as LP model

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!