Question: An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical

An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical jobs associated with various projects. Given below are the distances between the subcontractors and the projects.
\table[[,Projects],[Subcontractor,A,B,C],[Westside,50,36,16],[Federated,28,30,18],[Goliath,35,32,20],[Universal,25,25,14]]
How should the contractors be assigned so that total mileage is minimized?
Develop a spreadsheet optimization model with a two-way table and finds the least-mileage way of assignment. After running Solver, generate and save the answer report. Could you show ALL the formulas on excel.
 An electrical contractor pays his subcontractors a fixed fee plus mileage

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!