Question: An electronic health record system implementation was completed over a period of 18 months at a cost of $150,000. During the project, two change orders
An electronic health record system implementation was completed over a period of 18 months at a cost of $150,000. During the project, two change orders were approved using the change management process. Change order 113 was for $10,000 and required an additional two months to complete. Change order 123 was for $15,000 and required one additional month to complete. If the project charter established the budget at $95,000 dollars over 16 months, what was the status of the completed project?
Step by Step Solution
There are 3 Steps involved in it
To determine the status of the completed project lets break down the costs and time incurred 1 Origi... View full answer