Question: An electronic health record system implementation was completed over a period of 1 8 months at a cost of $ 1 5 0 , 0
An electronic health record system implementation was completed over a period of months at a cost of $ During the project, two change orders were approved using the change management process. Change order was for $ and required an additional two months to complete. Change order was for $ and required one additional month to complete. If the project charter established the budget at $ dollars over months, what was the status of the completed project?
Over budget and ahead of schedule
Under budget and ahead of schedule
Under budget and late
Over budget and late