Question: An electronics store uses a kanban system. Lead time for projectors is 7 days with daily demand of 5 projectors and a safety stock of

An electronics store uses a kanban system. Lead
An electronics store uses a kanban system. Lead time for projectors is 7 days with daily demand of 5 projectors and a safety stock of 1 day. Each kanban holds 8 projectors. The number of kanbans equals 5 07 4.5 8