Question: Lead time for computers is 7 days with daily demand of 7 computers and a safety stock of 1 day. Each kanban holds 8 computers.

Lead time for computers is 7 days with daily

Lead time for computers is 7 days with daily demand of 7 computers and a safety stock of 1 day. Each kanban holds 8 computers. What is the correct number of kanbans? not enough information 1 5 7 8