Question: an exception plan is triggered when the variance between actual and expected performance is: a beyond the threshold range set by the organization b beyond

an exception plan is triggered when the variance between actual and expected performance is: a beyond the threshold range set by the organization b beyond the threshold range set by the organization, and a formal meeting is arranged with all stakeholders c or beyond the threshold range by the organization and formal meeting is arranged with all stakeholders d within or beyond the threshold range set by the organization