Question: An existing oxidation ditch ( OD ) was designed and constructed on the basis of zero net sludge production to remove organic matter. The design

An existing oxidation ditch (OD) was designed and constructed on the basis of zero
net sludge production to remove organic matter. The design flow of the (OD) was
20000m3d. The design criteria were as follows:
S0=285mgBOD5L, required effluent concentration (S)=10mgBOD5L.
Y=0.50mgvssmgBODs,Ks=60mgBOD5L,Kd=0.02d-1,m=2.0d-1,
x=3000mg MLVSS/L.
A. What is the volume of the OD?
B. What is the value of waste activated sludge " Qw " and (c)?
C. What would be the value of " S "if the flow increased to 40000m3? day assuming
that X remains 3000mgL? What is your comment on the value of S ?
D. What are the values of S,x and FM if we operate the OD on a CFCMR model
instead of Zero net sludge model when the flow increases to 40000m3? day?
Assume a sludge age value (c) of 25 days.
E. What are the values of the sludge production" Px" and sludge waste " Q " for part
"D" above assuming xr=10000mg MLVSS/ L and xe=20mgssL?
Hint: use this equation to calculate "Px" for Part E.:
Px=Vxc
And this equation:
to calculate Qw.
An existing oxidation ditch ( OD ) was designed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!