Question: An increase in indirect costs could be directly attributable to an increase in what aspect of a project? a . Quality b . Direct costs

An increase in indirect costs could be directly attributable to an increase in what aspect of
a project?
a. Quality
b. Direct costs
c. Duration
d. All of the above
e. None of the above