Question: 1. An increase in indirect costs could be directly attributable to an increase in what aspect of a project? a. Quality b. Direct costs c.
1. An increase in indirect costs could be directly attributable to an increase in what aspect of a project?
a. Quality
b. Direct costs
c. Duration
d. All of the above
e. None of the above