Question: An indirect cost is A . A subcontractor cost because they do the work and the General Contractor ( GC ) is not directly doing
An indirect cost is
A A subcontractor cost because they do the work and the General Contractor GC is not directly doing the work
B Company owned construction equipment for excavation
C A concrete pump because it doesn't permanently stay on site
D A cost not directly attributable to the completion of an activity, which is typically allocated or spread across all activities sometimes called General Requirements
A tab or comparison sheet for subcontractors and suppliers during bidding allows for a much better vetting of scopes than just inputting the subcontractor's or supplier's quoted price?
A True
B False
The geotechnical report or soils report isn't really important to a project and is often considered just superfluous information?
A True
B False
When multiple supplier or subcontractor quotes are received for the same work, what is the most important reason to review the quote before considering their price?
A Make sure they are putting your favorite superintendent or foreman on the job
B They intend to take you out to lunch every Friday for the time they are on site
C They have the proper scope of work included
D They have the lowest bond rate
Which of the following is not an example of project documents that should be used to base a bid price on
A Phone call or email from a subcontractor or supplier stating that they spoke with
the engineer architect owner and they are an acceptable provider
B Addendum
C Invitation to Bid ITB and Bid Form
D Plans and Specifications
Step by Step Solution
There are 3 Steps involved in it