Question: An indirect cost is A . A subcontractor cost because they do the work and the General Contractor ( GC ) is not directly doing

An indirect cost is
A. A subcontractor cost because they do the work and the General Contractor (GC) is not directly doing the work
1 B. Company owned construction equipment for excavation
C. A concrete pump because it doesn't permanently stay on site
D. A cost not directly attributable to the completion of an activity, which is typically allocated or spread across all activities (sometimes called General Requirements)
A tab (or comparison) sheet for subcontractors and suppliers during bidding allows for a much better vetting of scopes than just inputting the subcontractor's or supplier's quoted price?
2
A. True
B. False
The geotechnical report (or soils report) isn't really important to a project and is often considered just superfluous information?
3
A. True
B. False
When multiple supplier or subcontractor quotes are received for the same work, what is the most important reason to review the quote before considering their price?
A. Make sure they are putting your favorite superintendent or foreman on the job
4 B. They intend to take you out to lunch every Friday for the time they are on site
C. They have the proper scope of work included
D. They have the lowest bond rate
Which of the following is not an example of project documents that should be used to base a bid price on?
A. Phone call or email from a subcontractor or supplier stating that they spoke with
5 the engineer/ architect/ owner and they are an acceptable provider
B. Addendum
C. Invitation to Bid (ITB) and Bid Form
D. Plans and Specifications
An indirect cost is A . A subcontractor cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!